Viseu
Portugal
The twin to the Fundão plant, in terms of its management and capacity. The plant is one we also built and developed together with our local partner FPT, and we supplied the boiler, supervised ELECNOR (EPC contractor) in the execution contract and, after its construction, we performed the operation and maintenance through Magestop. Its output is the same— 120,000 MWh of renewable energy from forest biomass—which represents an annual consumption of around 28,000 homes.
Technical information
-
Biomass-based electricity generating plant
-
Output 15 MWe
-
Location: Viseu (Portugal)
-
EPC: Elecnor
-
Project Developer: ENSO Energy Environment & Sustainability (as Gestamp Biomass) – FTP
-
Main milestones of the project and the boiler supply:
- - Started: June 2017
- - Ended: June 2019
-
O&M: Magestop (ENSO-FPT)


Viseu by night

Aerial view of works

Furnace openings (detail)

Stack, gas cleaning system and boiler on the back